Portishead railway reopening hangs in the balance as MetroWest project soars £100m over budget

PUBLISHED: 06:00 09 March 2017 | UPDATED: 06:09 09 March 2017

North Somerset Council leader Nigel Ashton believes construction work will begin in 2017.

North Somerset Council leader Nigel Ashton believes construction work will begin in 2017.

Archant

The future of Portishead’s railway reopening is in jeopardy, after it was revealed the project may not open until 2021 as costs have spiralled to more than £100million more than its original budget.

How could the project now be delivered?

MetroWest and North Somerset Council are advising the West of England’s Joint Transport Board to split the phase one project into three stages – A, B and C. If the board accepts their recommendation and appropriate funding is found, the stages will be progressed as follows:

A - Carrying out service improvements to the Severn Beach branch line and Bristol-Bath corridor.

B – Reopening the Portishead railway line to provide an hourly service between Portishead and Bristol Temple Meads, with trains running at 30mph.

C – Reopening the Portishead railway line to full capacity, meaning trains will run every half hour at 50mph.

The first phase of the MetroWest project - which is being partially funded by North Somerset Council – would see trains run half-hourly between Portishead and Bristol with the existing railway station at Pill reopened. The project would also include improvements to the Severn Beach branch line service and upgrading stations and services between Bristol Temple Meads and Bath.

It was initially expected to cost £58million when it was first announced, but the Times reported in January the cost was likely to be ‘considerably more’. The total cost of implementing phase one is now believed to be between £145-175million and has been deemed unaffordable by the team implementing it.

At a press briefing in Bristol yesterday (Wednesday), representatives from North Somerset and MetroWest announced the project’s fate would be sealed at the next meeting of the West of England Joint Transport Board on March 17.

MetroWest and the council are now urging the board to approve splitting the project into three stages – the second of which (stage B) would see trains run to Portishead once an hour in 2021 – in an attempt to reduce costs. The first stage (A) would see improvements made to connections between Bristol and Bath and the Severn Beach branch line, while the third stage (C) would eventually see trains run to Portishead every half an hour as originally promised.

According to MetroWest, the project’s initial estimated cost of £58million has risen by so much because the full impact of works needed to run trains through Avon Gorge every half an hour had been underestimated. The organisation claims running trains at 50mph through the Gorge – which is needed for a half-hourly service – is more expensive and difficult to implement than running them at 30mph once an hour, as this is the speed currently in place along the existing Portbury freight line.

The council’s director of development and environment, David Carter, said: “The process we are suggesting and recommending is to look at stages A and B as they would significantly reduce the cost.

“We believe the work will be done and it will still be delivered in 2021, assuming the funding can be found.

“Stages A and B will still need to attract additional funding, but we believe there will be a significant reduction for A and B compared to C. However, until we have done the work, it is difficult to say exactly what that is.

“We are working with Network Rail and the Department for Transport to close that funding gap.”

For a full reaction to the announcement, pick up a copy of next week’s Times.

Other News Stories

12:00

The organisers of Eat: Portishead say they have been ‘blown away’ by the success of their first Portishead festival.

Read more

Historic documents about how Clevedon Pier was founded, and its changes in fortune and ownership, will be catalogued thanks to a grant.

Read more

North Somerset Council could have a ‘Grenfell Tower situation’ on its hands if it continues to allow highly-flammable fuel to be stored just metres away from homes in Portishead, according to members.

Read more

First Bristol will start running its new M2 bus service from September.

Read more
10:00

Dogs and their owners will be able to swim together at Portishead Open Air Pool next month.

Read more
Yesterday, 17:00

A Clevedon children’s charity has been given thousands of pounds to introduce new digital learning diaries.

Read more
Yesterday, 16:00

Plans to flatten a pub and replace it with a petrol station have been slated by a rival business.

Read more
Yesterday, 14:00

Firefighters will clean a 19th century Portishead lighthouse this weekend.

Read more
Yesterday, 13:00

Children’s Hospice South West and the Salvation Army in Pill are two charities to benefit from a week of fundraising by Southern Co-op.

Read more
Yesterday, 12:00

A councillor has hit back at claims of ‘dereliction of duty’ by a committee responsible for scrutinising major housing plans.

Read more

Most Read News

Read Online

Image
Read the North Somerset Times e-edition E-edition

Local Weather

Overcast

Overcast

max temp: 21°C

min temp: 16°C

Useful Links

Advertise in the paper
Submit a Story
Subscribe to the paper
Competitions
Send Your Letters
Order Photos
Family notices
iwitness24
Facebook
Twitter
Reader Travel

Clevedon Tide report

Family Notices 24

Newsletter Sign Up

North Somerset Times twice-weekly newsletter
Sign up to receive our regular email newsletter

Our Privacy Policy

Show Job Lists

Find planning applications